Ringkasan Progres Proyek
Modernisasi CCTV dan Access Control Area East Batch #5 Tahun 2026 — Telkomsel (TSEL)
Realisasi (rata2)
28.98%
seluruh 29 site
Target Kumulatif
4.11%
s/d W1
Deviasi
+24.87%
di atas target
Status Site
Selesai2
On track24
Tertinggal0
Belum mulai3
Kurva-S — Rencana vs Realisasi Kumulatif (%)
Progres per Komponen Pekerjaan (%)
Rekap per Area
| Area | Site | Aktual | Target | Dev |
|---|---|---|---|---|
| Area 3 | 16 | 38.1% | 5.6% | +32.5 |
| Area 4 | 13 | 17.8% | 2.3% | +15.4 |
Site Paling Tertinggal
Buka Master Data →| Lokasi | Region | Aktual | Target | Deviasi |
|---|---|---|---|---|
| GRAPARI SARMI | PUMA | 0.00% | 0.00% | +0.00% |
| GRAPARI SORONG | PUMA | 0.00% | 0.00% | +0.00% |
| GRAPARI TERNATE | SULAWESI | 0.00% | 0.00% | +0.00% |
| BRANCH PANGKALAN BUN | KALIMANTAN | 0.01% | 0.00% | +0.01% |
| GRAPARI MATARAM | BALNUS | 16.25% | 3.37% | +12.88% |
| GRAPARI JIMBARAN | BALNUS | 16.26% | 3.37% | +12.89% |
| GRAPARI PEKALONGAN | JAWA TENGAH | 18.75% | 3.37% | +15.38% |
| GRAPARI MAKASSAR BALAI KOTA | SULAWESI | 20.00% | 3.37% | +16.63% |