Monitoring CMM — 29 Site
WEEK 4, 25 Agustus - 8 September 2026
← Master Data

TTC GOMBEL

Area 3 · JAWA TENGAH · JAWA TENGAH

Progres Total
24.38%
Target W3
10.10%
Deviasi
+14.28%
Bill of Quantity
11
CCTV Indoor
5
CCTV Outdoor
7
Access Reader

Progres per Komponen — isi % penyelesaian, tersimpan otomatis

KomponenBobot % SelesaiKontribusi
INSTALASI KABEL 40% 16.25%
TEST CONTINUITY 20% 8.13%
PEMASANGAN UNIT 10% 0.00%
TERMINASI 10% 0.00%
SETTING 10% 0.00%
TROUBLESHOOT 6% 0.00%
TESCOM & BAST 4% 0.00%
 

Kurva Target vs Realisasi Mingguan (site ini)