Monitoring CMM — 29 Site
WEEK 4, 25 Agustus - 8 September 2026
← Master Data

GRAPARI BANYUWANGI

Area 3 · JAWA TIMUR · JAWA TIMUR

Progres Total
25.63%
Target W3
10.10%
Deviasi
+15.53%
Bill of Quantity
10
CCTV Indoor
3
CCTV Outdoor
0
Access Reader

Progres per Komponen — isi % penyelesaian, tersimpan otomatis

KomponenBobot % SelesaiKontribusi
INSTALASI KABEL 40% 17.50%
TEST CONTINUITY 20% 8.13%
PEMASANGAN UNIT 10% 0.00%
TERMINASI 10% 0.00%
SETTING 10% 0.00%
TROUBLESHOOT 6% 0.00%
TESCOM & BAST 4% 0.00%
 

Kurva Target vs Realisasi Mingguan (site ini)