TS
Monitoring CMM — 29 Site
WEEK 4, 25 Agustus - 8 September 2026
← Master Data

GRAPARI MADIUN

Area 3 · JAWA TIMUR · JAWA TIMUR

Progres Total
39.22%
Target W3
10.10%
Deviasi
+29.12%
Bill of Quantity
0
CCTV Indoor
0
CCTV Outdoor
0
Access Reader

Progres per Komponen — isi % penyelesaian, tersimpan otomatis

KomponenBobot % SelesaiKontribusi
INSTALASI KABEL 40% 33.73%
TEST CONTINUITY 20% 5.49%
PEMASANGAN UNIT 10% 0.00%
TERMINASI 10% 0.00%
SETTING 10% 0.00%
TROUBLESHOOT 6% 0.00%
TESCOM & BAST 4% 0.00%
 

Kurva Target vs Realisasi Mingguan (site ini)