Progres Total
100.00%
Target W3
0.00%
0.00%
Deviasi
+100.00%
+100.00%
Bill of Quantity
8
CCTV Indoor
1
CCTV Outdoor
0
Access Reader
Progres per Komponen — isi % penyelesaian, tersimpan otomatis
| Komponen | Bobot | % Selesai | Kontribusi |
|---|---|---|---|
| INSTALASI KABEL | 40% | 40.00% | |
| TEST CONTINUITY | 20% | 20.00% | |
| PEMASANGAN UNIT | 10% | 10.00% | |
| TERMINASI | 10% | 10.00% | |
| SETTING | 10% | 10.00% | |
| TROUBLESHOOT | 6% | 6.00% | |
| TESCOM & BAST | 4% | 4.00% |